Building project; application for a building permit

Building application online
Building application online - Submit missing information and documents online
Criteria catalog - Submit a declaration of fulfillment online
Apply for a partial building permit online
Please note in particular our information under:
  • Brief description

    You generally need a building permit to erect, modify or change the use of a facility. Only in exceptional cases is planning permission not required.

  • Description

    A building permit grants you the right to construct, modify or change the use of a facility for projects that require approval. It is a state declaration that the project does not conflict with public law, which must be examined in the building inspection procedure. However, this only applies at the time of the decision.

    Projects not requiring approval

    A project is not subject to approval if it is exempt from the approval process or is exempt from approval. Projects that are exempt from the approval process are those that have minimal relevance under building code regulations. Projects may be exempt from approval if, in particular, they are not special structures and comply with a qualified zoning plan. However, this depends on the municipality. If the municipality requires that an approval process be carried out, the construction project is not exempt from approval.

    If the project does not require approval, you do not need to apply for planning permission. You would not be granted such a permit.

    Consequences of not having the required building permit

    If you erect or modify a facility or change its use without the required building permit, the responsible lower building supervisory authority can intervene and take appropriate measures. This can go as far as ordering the removal of the facility.

    Special information for the Bad Tölz-Wolfratshausen district

    Please give priority to using the online services via the buttons above.

    • Building application online.
    • Apply for a partial building permit online.
    • Building application online - Submit missing information and documents online.

    The following documents are available in the "Forms" section:

    • FAQ on the digital planning application process
    • Statement on Groundwater Impact in the Building Permitting Process

    Among the links you will find the following important pages:

    • Bavarian Renewable Energies Procedure Manual.
    • Building Permit Process - Our Topic Page.

     

  • Prerequisites

    The building permit applied for will only be granted if the project is subject to approval. Furthermore, the project must not conflict with any public law regulations.

  • Deadlines

    none
  • Required documents

    Current cadastral extract

    Site plan, if applicable

    Not required if the application is limited to changes to structural elements that do not alter exterior walls, roofs, or the building’s use.

    Building specifications

    If the building permit application is submitted digitally, the required information is included in the online wizard.

    If applicable, fire safety certification

    Required only if it is subject to building code review and is not already included in the other construction documents.

    If applicable, structural stability certification

    Required only for special structures, provided that structural stability is subject to building code review.

    If applicable, declaration of compliance with the criteria catalog (see “Forms” for the form)

    Only for special structures, if the declaration indicates that the structural stability verification does not need to be reviewed by the building authority. If the building permit application is submitted digitally, the structural engineer may also submit the declaration digitally using an online wizard, provided that it is available under “Online Procedures.”

    Any required information regarding secured utility connections for water and energy supply, wastewater disposal, and transportation access

    Required only if the construction project cannot be connected to a public water or energy supply system or to a public wastewater treatment facility. Also required if the construction project does not abut a public transportation right-of-way with sufficient width.

    If applicable, calculation of the permissible and planned extent of building use

    Required only within the scope of a zoning plan that contains provisions regarding this.

    If applicable, consent to the assumption of setback requirements (see “Forms” for the form)

    If applicable, applications for exemptions

    If applicable, additional documents

    Depending on the construction project, additional documents may be required, such as a tree inventory declaration. However, this is only required if the municipality requests it.
  • Forms

  • Costs

    The fees for a building permit amount to between 1 per thousand and 4 per thousand of the building costs, depending on the type of building project and the type of approval procedure. You must also pay fees if your building application is rejected or withdrawn. In this case, however, the fees are reduced.

    If planning permission is granted for a change of use of structural facilities, the fee is between EUR 40 and EUR 5,000, depending on the administrative costs incurred.

  • Legal basis

  • Legal remedy

    If you do not receive the building permit you applied for, you can file an administrative appeal. This must be aimed at obtaining the requested building permit.

    An objection is not possible.

  • Further links

  • Procedure

    Written submission

    First of all, please note that in the case of building applications for the construction and alteration of buildings, the building documents must be prepared by an authorized draftsman (architect, civil engineer; for smaller construction projects, especially detached and semi-detached houses, also master craftsmen in the building and carpentry trades and state-certified technicians in the field of construction engineering).

    • If necessary, contact the municipality in whose area the building plot is located before submitting your application if you have any questions about the permissibility of your project.
    • Involve your neighbors by submitting the site plan and the construction drawings for their approval. Any consent must be given in writing.
    • Then submit the building application with the required documents to the responsible lower building supervisory authority (district offices, independent cities, large district towns and certain larger municipalities).
    • Submit the building application in triplicate using the forms provided. If the lower building supervisory authority is also the municipality, two copies are sufficient.
    • An oral application is not possible.
    • The application must be signed by the client and the authorized designer.
    • The lower building supervisory authority examines the application and decides on it.
    • If the lower building supervisory authority is not itself a municipality, it shall involve the municipality in the decision on the municipal consent.
    • Before making a decision, the lower building supervisory authority must involve the authorities whose involvement or consultation is required by law for the decision on the building application or without whose opinion the approvability of the building application cannot be assessed (e.g. the lower immission control authority, the lower water authority or the road traffic authority).

    Digital submission

    Digital submission of building applications is not yet possible throughout Bavaria. When selecting a location, the link to the online procedure will be displayed if it is already available.

    • After involving the neighbors, the building application can be submitted digitally using the online assistant.
    • The predefined building application and building description forms are replaced by the queries in the online assistant.
    • The building documents are uploaded to the online assistant in electronic form (files in PDF format).
    • The signatures of the client and the authorized designer are replaced by authentication using the "BayernID" or "My company account" user account.
    • In particular, the (large-format) construction drawings do not need to be signed. They can therefore be generated as a file directly in the CAD system of the design author.
    • In the case of building applications for which the building documents must be prepared by an authorized draftsman, the latter must authenticate himself and submit the building application on behalf of the client.
  • Notes

    Under no circumstances should you start work on a project that requires approval without having applied for and obtained the necessary building permit.

  • Processing time

    The processing time depends on the scope and complexity of the application, the number of agencies involved and the current workload of the authority.