Building project; application for an isolated exemption from the development plan

Apply for isolated deviation, exemption or exception online
Please note in particular our information under:
  • Brief description

    If your non-procedural project conflicts with the provisions of a development plan, you can apply for an exemption under certain conditions.
  • Description

    Under certain conditions, you can apply for an exemption from the provisions of a development plan for your project. An exemption from the provisions of a development plan is usually dealt with together with a building application. However, an exemption from the provisions of a development plan can also be applied for for projects that do not require a procedure. In this case, an isolated decision is made on the exemption.

    Even if your project is exempt from the provisions of a development plan, it must still comply with the public law requirements.

    Exemption from the provisions of the development plan is a discretionary decision. If the requirements for exemption are met in principle, exemption can still be denied if necessary.

    Special information for - District of Bad Tölz Wolfratshausen

    Please give priority to using the online service offered via the button above for "Apply for isolated deviation, exemption or exception online".
    In the Forms section you will find the "FAQ on the digital planning application procedure" and under the further links you will find the reference to our "Planning application procedure" topic page.

  • Prerequisites

    You can apply for an isolated exemption from the development plan if

    • your project is exempt from procedures,
    • it does not affect the basic principles of planning,
    • the deviation is also compatible with public interests when neighboring interests are taken into account and
      • reasons of public welfare, including the housing needs of the population, the need to accommodate refugees or asylum seekers, the need for facilities for social purposes and the need for a rapid expansion of renewable energies, which require exemption
      • the deviation is justifiable in terms of urban development or
      • the implementation of the development plan would lead to an obviously unintended hardship.
  • Deadlines

    none
  • Required documents

    Current cadastral extract

    Site plan

    (M 1 : 1,000 or 1 : 5,000)



    Construction drawings

    If necessary, further documents

    If required for the decision on the isolated exemption.
  • Forms

    Special information for - District of Bad Tölz Wolfratshausen
  • Costs

    The fees amount to 10% of the benefit you stand to gain from the exemption, but at least EUR 75.
  • Legal basis

  • Legal remedy

    You can challenge the municipality's decision on the isolated exemption from the development plan by filing a complaint with the administrative court.

  • Further links

  • Procedure

    Written submission

    • Submit your application for an isolated exemption from the provisions of a development plan to the relevant local authority.
    • Also submit a justification and the required documents. The documents required are those that the municipality needs to be able to assess the facts of the case.
    • A specific form is not required.
    • An oral application is not possible.
    • If the exemption affects regulations that serve to protect neighbors, you should submit the application to your neighbors and obtain their consent before submitting it.
    • The municipality will review your application and make a decision. You will receive a written decision.

    Digital submission

    Digital submission of applications for isolated exemption is not yet possible throughout Bavaria. When selecting a location, the link to the online procedure will be displayed if it is already offered.

    • The application for isolated exemption from the provisions of a development plan can be submitted digitally using the online assistant. The documents are uploaded to the online assistant in electronic form (files in PDF format). Signatures are replaced by authentication using the "BayernID" user account or "My company account".
    • If the application first reaches the lower building supervisory authority , it will immediately forward it to the responsible municipality.
  • Processing time

    The processing time depends on the scope and complexity of the project as well as the current workload of the municipality.