Building project; application for extension of a building permit or preliminary decision
Brief description
You can have your building permit, partial building permit or preliminary decision extended if necessary.
Description
Building permits, partial building permits and preliminary decisions are only valid for a certain period of time.
If you are unable to start your approved project within 4 years, you can apply for an extension. If you do not receive planning permission for the same project within 4 years of receiving a preliminary decision, you can apply for an extension of the preliminary decision.
The extension period is up to four years, multiple extensions are possible.
Special information for - District of Bad Tölz WolfratshausenPlease give priority to using the online service offered via the button above for "Apply for extension of a building permit or preliminary decision online".
In the Forms section you will find the "FAQ on the digital building application procedure" and under the further links you will find the reference to our topic page "Building application procedure".Prerequisites
An extension of the period of validity of a building permit or partial building permit is to be assessed on the basis of the same requirements as the initial granting. The project must therefore still be subject to approval at the time of the lower building supervisory authority's decision on the extension. In addition, the project must comply with public law regulations, which must be examined in the approval procedure.
This applies accordingly to the extension of the preliminary decision.
If the legal situation changes after the permit or preliminary decision has been issued, the extension must be checked against the new legal situation.
Deadlines
Your building permit or partial building permit will expire if you have not started work on the project within 4 years of it being granted or if you have interrupted construction work for 4 years. Your application for renewal must be received by the responsible lower building supervisory authority before the expiry date. Receipt by the municipality is not sufficient to meet the deadline.
Your preliminary decision is valid for 4 years. Your application for extension must be received by the responsible lower building supervisory authority before the expiry of the period of validity. Receipt by the municipality is not sufficient to meet the deadline.
Forms
Special information for - District of Bad Tölz Wolfratshausen- FAQ on the digital planning application process
All important questions about the digital building application process are answered in detail.
- FAQ on the digital planning application process
Costs
You will have to pay a fee of between EUR 40 and EUR 10,000 for the extension, depending on the administrative costs incurred.Legal basis
- Art. 69 Bavarian Building Regulations (BayBO)
Period of validity of the building permit and the partial building permit
- Art. 71 Bavarian Building Regulations (BayBO)
Preliminary decision
- Ordinance on the digital submission of building authority applications and notifications (Digital Building Application Ordinance - DBauV)
- Art. 69 Bavarian Building Regulations (BayBO)
Legal remedy
You can appeal to the administrative court against a decision by the lower building supervisory authority regarding the extension.
Further links
Special information for - District of Bad Tölz Wolfratshausen- Building application procedure
Information on the application procedure, documents, etc.
- Building application procedure
Procedure
Written submission
- Apply in writing to the responsible lower building supervisory authority to extend the validity of your building permit, partial building permit or preliminary decision.
- An oral application is not possible.
- The lower building supervisory authority will then decide on your application and inform you of the result.
- If the lower building supervisory authority only decides on your application after the expiry of the period of validity, your building permit, partial building permit or preliminary decision will become temporarily invalid. These will then only be reinstated once the lower building supervisory authority has made a positive decision.
Digital submission
Digital submission of applications for renewal is not yet possible throughout Bavaria. When selecting a location, the link to the online procedure will be displayed if it is already offered.
- The application for extension can be submitted digitally to the lower building supervisory authority using the online assistant.
- Attachments are uploaded in electronic form (files in PDF format) in the online assistant.
- The signatures are replaced by authentication using the "BayernID" user account or "My company account".
Notes
Apply for an extension in good time if it is foreseeable that the period of validity will not be sufficient.
Processing time
The processing time depends on the scope and complexity of the project and the current workload of the lower building supervisory authority.