Immission control; notification of an emission-relevant change to a medium-sized combustion, gas turbine and internal combustion engine plant

  • Brief description

    Do you want to make an emission-relevant change to a medium-sized combustion plant, gas turbine or combustion engine plant? Then you must notify the responsible immission control authority.

  • Description

    If you wish to carry out an emission-relevant modification to a medium-sized combustion plant, gas turbine or combustion engine plant, you must notify the responsible immission control authority in advance.

    The obligation to notify generally applies to all combustion plants with a rated thermal input of at least 1 MW and less than 50 MW, whether or not they require a permit.

    In the case of aggregated combustion plants, you must notify the planned commissioning if the combined thermal input of the combustion plant is more than 1 MW and less than 50 MW.

    The authority responsible for you will then enter the information you provide in a register of installations, which is publicly accessible.

  • Prerequisites

    You would like to carry out an emission-relevant modification to a medium-sized combustion, gas turbine or internal combustion engine system.

  • Deadlines

    The emission-relevant modification of an installation must be reported immediately, but at the latest within one month.

  • Required documents

    Required document/s

    Complete written or electronic notification

  • Costs

    There are no costs.

  • Legal basis

  • Legal remedy

    None. The administrative service is a real act against which no legal remedy is possible.

  • Procedure

    • You submit your notification to the authority responsible for you in writing or electronically.
    • The competent authority will examine your notification and request further documents if necessary.
    • Once the notification and the complete documentation have been received, the competent authority will update the details of your installation in the installation register.
  • Notes

    You are committing an administrative offense if you do not submit the notification, or do not submit it correctly, completely, in the prescribed manner or on time.

  • Processing time

    There is no deadline for processing.