Immission control; notification of the operation or commissioning of a medium-sized combustion, gas turbine and internal combustion engine plant
Brief description
If you want to operate or commission a medium-sized combustion plant, gas turbine or internal combustion engine plant, you must notify the competent authority.
Description
As the operator of a combustion plant (medium-sized combustion plant, gas turbine and internal combustion engine plant) within the meaning of the Forty-Fourth Ordinance on the Implementation of the Federal Immission Control Act (44th BImSchV) with a rated thermal input of at least 1 MW and less than 50 MW, you are obliged to notify the competent authority in writing or electronically of the intended operation prior to commissioning.
The operation of an existing combustion plant must be reported to the competent authority in writing or electronically by December 1, 2023.
The display must contain the following information:
- Combustion heat output of the combustion plant (in megawatts)
- Type of combustion plant (diesel engine plant, gas turbine, dual-fuel engine plant, other engine plant, other combustion plant)
- Type of fuel used and respective share of total energy input
- Date of commissioning of the firing system
- the NACE code to which the other activity is to be assigned, in accordance with Annex I to Regulation (EC) No 1893/2006
- expected number of annual operating hours of the combustion plant and average operating load
- where use is made of a scheme for installations with few operating hours: a declaration signed by the operator stating that the combustion plant will not be in operation for more than the number of hours referred to in those paragraphs
- if use is made of a regulation for emergency operation: a declaration signed by the operator stating that the combustion plant will only be in operation in an emergency;
- Name and registered office of the operator and location of the installation with address
- Geocoordinates of the chimney and height above ground
Special information for - District of Bad Tölz WolfratshausenUnder Forms you will find the "Form register sheet for the notification of a combustion plant in accordance with the 44th BlmSchV".
Under the further links you will find the reference to our topic page "Register of combustion plants 44th BlmSchV" with summarized information.Prerequisites
You operate a medium-sized combustion, gas turbine or internal combustion engine system or would like to commission one.
Deadlines
The notification must be submitted before commissioning a new system.
The operation of an existing system must be reported by December 1, 2023.
Required documents
if applicable, a declaration signed by the operator stating that the combustion plant will not be in operation for more than the number of hours specified
if applicable, a declaration signed by the operator stating that the combustion plant will only be in operation in an emergencyForms
Special information for - District of Bad Tölz WolfratshausenCosts
There are no costs.
Legal basis
- Annex 1 (to § 6) Forty-fourth Ordinance on the Implementation of the Federal Immission Control Act (Ordinance on Medium-Sized Combustion, Gas Turbine and Internal Combustion Engine Plants - 44th BImSchV)
Information to be provided by the operator to the competent authority
- § Section 6 Forty-fourth Ordinance on the Implementation of the Federal Immission Control Act (Ordinance on Medium-Sized Combustion, Gas Turbine and Internal Combustion Engine Plants - 44th BImSchV)
- Annex 1 (to § 6) Forty-fourth Ordinance on the Implementation of the Federal Immission Control Act (Ordinance on Medium-Sized Combustion, Gas Turbine and Internal Combustion Engine Plants - 44th BImSchV)
Legal remedy
The administrative service is a real act against which no legal remedy is possible.
Further links
Special information for - District of Bad Tölz Wolfratshausen- Register of combustion plants 44th BlmSchV
As the competent authority, the Bad Tölz-Wolfratshausen District Office must keep a register with information on every combustion plant to be registered in accordance with § 6 of the 44th BImSchV pursuant to § 36 of the 44th BImSchV and must also make the information contained in the register publicly accessible in accordance with Directive 2003/4/EC.
- Register of combustion plants 44th BlmSchV
Procedure
The notification must be submitted in writing by post or electronically to the competent authority.
Once the notification has been checked, it is entered into a register of installations (this can also be found under the heading "Forms and information sheets"). The information contained in the register of installations is made publicly accessible in accordance with Section 36 of the 44th BImSchV and the provisions on access to environmental information (Environmental Information Act - UIG).
Notes
You are committing an administrative offense if you do not submit the notification, or do not submit it correctly, completely, in the prescribed manner or on time.
Related services
- Immission control; notification of an emission-relevant change to a medium-sized combustion, gas turbine and internal combustion engine plant
- Immission control; notification of the final decommissioning of a medium-sized combustion, gas turbine and internal combustion engine plant
- Immission control; notification of change of operator of a medium-sized combustion, gas turbine and internal combustion engine plant