Excavation; application for a partial excavation permit

Apply for a partial building permit online
Please note in particular our information under:
  • Brief description

    You can apply for a partial excavation permit if you have submitted an excavation application but have not yet received an excavation permit. This allows you to obtain a permit for individual parts of the project in advance.

  • Description

    You may only start excavating once the excavation permit has been issued. This can take longer, especially for larger projects. With a partial excavation permit, you can start individual sections of the project in advance. However, this only applies to the section for which you have received the partial excavation permit.

    The part of your project that is already covered by the partial excavation permit will no longer be decided as part of the excavation permit.

    Special information for - District of Bad Tölz Wolfratshausen

    Please give priority to using the online service offered via the "Apply for partial building permit online" button above.
    In the Forms section you will find the "Annex to the partial building permit application" and under the further links you will find the reference to our topic page "Building permit application procedure".

  • Prerequisites

    You must first apply for an excavation permit. Only then can you apply for a partial excavation permit for part of the project.

    The partial excavation permit applied for will only be granted if the project is subject to approval. Furthermore, the part of the project for which the partial excavation permit is requested must not conflict with any regulations under public law. In addition, the lower excavation authority must determine that the overall excavation project is generally permissible. The granting of the partial excavation permit is at the discretion of the lower excavation authority.

  • Deadlines

    The partial excavation permit must be applied for before the excavation permit is issued.

  • Required documents

    Site plan

    Construction drawings

    Building description
  • Forms

    Special information for - District of Bad Tölz Wolfratshausen
  • Costs

    The fees for a partial excavation permit depend on the amount of excavated material that can be used:

    • For sand and gravel pits, quarries and similar excavations for the extraction of excavated material for projects with usable excavated material up to 50,000 m³ EUR 100 plus EUR 25 per 1,000 m³ or part thereof
    • For sand and gravel pits, quarries and similar excavations for the extraction of excavated material for projects with usable excavated material over 50,000 m³ up to 500,000 m³ EUR 1,350 plus EUR 55 for every 10,000 m³ or part thereof in excess of 50,000 m³
    • For sand and gravel pits, quarries and similar excavations for the extraction of excavated material for projects with usable excavated material in excess of 500,000 m³ EUR 3,825 plus EUR 110 for every 50,000 m³ or part thereof in excess of 500,000 m³
    • For other independent excavations EUR 50 to 2,000

    If an environmental impact assessment is to be carried out, the fee is increased by 40%. The fee is offset against the subsequent excavation permit fee.

  • Legal basis

  • Legal remedy

    If you do not receive the partial excavation permit you have applied for, you can file an administrative appeal. This must be directed at the granting of the partial excavation permit applied for. However, it is at the discretion of the lower excavation authority to grant the partial excavation permit. In principle, you do not have a legal claim to the granting of the permit, even if there are no public law regulations that conflict with the part of the project for which the partial excavation permit is requested.

    An objection is not possible.

  • Further links

  • Procedure

    Written submission

    • After submitting your excavation application, submit the partial excavation application with the required documents in writing to the lower excavation authority (district offices, independent cities) in whose area the excavation site is located.
    • A specific form is not required.
    • The application must be made in writing, an oral application is not possible.
    • The lower excavation authority examines the application and decides on it.

    Digital submission

    Digital submission of applications for partial excavation permits is not yet possible throughout Bavaria. When selecting a location, the link to the online procedure is displayed, if it is already offered.

    • The application for a partial excavation permit can be submitted digitally to the lower excavation authority using the online assistant.
    • The excavation plan is uploaded to the online assistant in electronic form (files in PDF format). Signatures are replaced by authentication using the "BayernID" user account or "My company account".
  • Notes

    A partial excavation permit can be particularly useful if you want to start excavation soon, but it is foreseeable that it will take longer to obtain the excavation permit. A granted excavation permit also contains the statement that the overall project is generally eligible for approval. In individual cases, however, you may not receive the requested excavation permit at a later date.

  • Processing time

    The processing time depends on the scope and complexity of the application, the number of agencies involved and the current workload of the authority.