Immission control; notification that the threshold values have been exceeded for the first time for installations with solvent consumption that do not require a permit

  • Brief description

    Do you want to operate a plant that does not require a permit and uses solvents and exceed the threshold values in Annex I of the 31st BImSchV for the first time? Then you must notify the responsible immission control authority in advance.

  • Description

    If you operate an installation that does not require a permit and uses solvents and exceeds the threshold values in Annex I of the 31st BImSchV for the first time, you must notify the responsible immission control authority in advance.
    The obligation to notify applies to all installations not requiring a permit that are already in operation. The solvent consumption must exceed the threshold values according to Annex I of the 31st BImSchV for the first time.
    The activity according to Annex II of the 31st BImSchV is decisive for the threshold value.
     

  • Prerequisites

    You operate a plant whose solvent consumption exceeds the threshold values in Annex I of the 31st BImSchV for the first time.

  • Deadlines

    You must submit the notification no later than 6 months after exceeding the threshold values for the installation for the first time.
  • Required documents

    Required document/s

    Complete display with the relevant data for the system

  • Costs

    There are no costs.

  • Legal basis

  • Legal remedy

    None. The administrative service is a real act against which no legal remedy is possible.

  • Procedure

    • You submit your notification with the relevant data for the system to the authority responsible for you
    • The competent authority will examine your notification
    • If necessary, the competent authority will request further documents from you
       
  • Notes

    You are committing an administrative offense if you do not submit the notification or do not submit it correctly, completely or on time.

  • Processing time

    There is no processing deadline.