Do you want to operate a plant that does not require a permit and uses solvents and exceed the threshold values in Annex I of the 31st BImSchV for the first time? Then you must notify the responsible immission control authority in advance.
Description
If you operate an installation that does not require a permit and uses solvents and exceeds the threshold values in Annex I of the 31st BImSchV for the first time, you must notify the responsible immission control authority in advance.
The obligation to notify applies to all installations not requiring a permit that are already in operation. The solvent consumption must exceed the threshold values according to Annex I of the 31st BImSchV for the first time.
The activity according to Annex II of the 31st BImSchV is decisive for the threshold value.
Prerequisites
You operate a plant whose solvent consumption exceeds the threshold values in Annex I of the 31st BImSchV for the first time.
Deadlines
You must submit the notification no later than 6 months after exceeding the threshold values for the installation for the first time.Required documents
Required document/s
Complete display with the relevant data for the system
Costs
There are no costs.
Legal basis
Legal remedy
None. The administrative service is a real act against which no legal remedy is possible.
Procedure
- You submit your notification with the relevant data for the system to the authority responsible for you
- The competent authority will examine your notification
- If necessary, the competent authority will request further documents from you
Notes
You are committing an administrative offense if you do not submit the notification or do not submit it correctly, completely or on time.
Processing time
There is no processing deadline.