Immission control; notification of the commissioning of an installation not requiring a permit with a solvent consumption above the threshold values

  • Brief description

    Do you want to commission a system that does not require a permit and uses solvents above the threshold values? Then you must notify the responsible immission control authority in advance.

  • Description

    If you wish to commission an installation that does not require a permit with a solvent consumption above the threshold values, you must notify the responsible immission control authority in advance.
    The obligation to notify applies to all installations that do not require a permit and whose solvent consumption exceeds the threshold values in Annex I of the 31st BImSchV.
    The threshold value is determined by the activity according to Annex II of the 31st BImSchV.
     

  • Prerequisites

    You wish to commission a system whose solvent consumption exceeds the threshold values in Annex I of the 31st BImSchV.

  • Deadlines

    You must submit the notification prior to the intended commissioning of the system.

  • Required documents

    Required document/s

    Complete display with the relevant data for the system.

  • Costs

    There are no costs.

  • Legal basis

  • Legal remedy

    None. The administrative service is a real act against which no legal remedy is possible.

  • Procedure

    • You submit your notification with the relevant data for the system to the authority responsible for you
    • The competent authority will examine your notification
    • If necessary, the competent authority will request further documents from you
  • Notes

    You are committing an administrative offense if you do not submit the notification or do not submit it correctly, completely or on time.

  • Processing time

    There is no processing deadline.